Somerset County in coordination with the North Jersey Transportation Planning Authority (NJTPA) and the New Jersey Department of Transportation (NJDOT) are advancing the design for the replacement of the Picket Place Bridge. The project goals are to address the structural deficiencies of the bridge and increase safety for the traveling public.
The Local Preliminary Engineering (LPE) Phase is the second step of the project development process. It involves performing engineering tasks and technical environmental studies with the goal of refining the Preliminary Preferred Alternative (PPA), securing the environmental document [i.e. National Environmental Policy Act (NEPA) document] and graduating the project to Final Design (FD). Based on the PPA, a number of activities are simultaneously set in motion in this phase: community involvement (meetings with affected property or business owners), agency consultation, environmental documentation, design level mapping and design services. To obtain the community consensus, a public information meeting will be conducted, which may lead to minor adjustments to the PPA.
Local Capital Project Delivery (LCPD) Program
Local Capital Project Delivery Process
1. Local Concept Development | 2. Local Preliminary Engineering | 3. Final Design/ROW Acquisition | 4. Construction |
---|---|---|---|
Purpose & Need Statement | Approved Design Exception Report | Construction Contract Documents & PS&E Package | Completed Construction |
Data Collection & Environmental Screening Report | Cost Estimates (Final Design, ROW & Construction) | Environmental Reevaluations | As-Built |
Selection of Preliminary Preferred Alternative | Approved Environmental Document | Environmental Permits | Update & Finalize Design Communications Report |
Concept Development Report | Approved Project Plan | Acquisition of ROW | Close-out Documentation |
NEPA Classification | Preliminary Engineering Report | Update Design Communications Report | Continued Public Outreach & Involvement |
Create Design Communications Report | Update Design Communications Report | Continued Public Outreach & Involvement | |
Initial Public Outreach & Involvement | Continued Public Outreach & Involvement |